Week 7 - December 31, 2012 - January 6, 2013

Happy New Year to everyone and to progress on the house.  Similar to last week, there isn't much visual progress.  They did back fill up against the foundation walls and poured the concrete floor in the garage attached to the house.  On a positive note, a majority of the huge piles of dirt that have been surrounding the foundation are now gone, which I'm sure our neighbors appreciate!






This is the floor in the garage, they poured the concrete and then covered to protect against the cold weather.


Weekly Progress Shots

Shot from South Side of Lot

Shot from Center of Lot

Shot from North Side of Lot